Pre-Construction Anti-Termite Treatment: When, Where and What to Check

Termite treatment starts before the footing PCC and follows the building up: trench bottom and sides, backfill against the foundation, the plinth fill under the floor, and the wall-floor junctions, as set out in IS 6313 (Part 2). A licensed applicator does it with a registered chemical, stage by stage.

WhatsApp
Open tins of coloured paint, close-up
Waterproofing & termite protection

How we supply it: Anti-termite treatment is arranged through a partner licensed pest control operator who quotes, treats and bills it and pays us a referral commission. We share your excavation and PCC dates with the operator, so each stage is treated just before our 40 mm jalli and M-Sand for that pour arrive.

Also calledanti termite treatment, pre-construction termite treatment, termite control, soil treatment
Tamilகரையான் தடுப்பு
StandardIS 6313 (Part 2) pre-constructional treatment, IS 6313 (Part 3) existing buildings

In one line: Pre-construction anti-termite treatment is soil treatment with a registered termiticide, applied in stages as the foundation and floor are built, to form a chemical barrier between subterranean termites and the structure.

What the treatment protects

Pre-construction anti-termite treatment is soil treatment with a registered termiticide, applied in stages as the foundation and floor are built, to form a chemical barrier between subterranean termites and the structure.

Subterranean termites, கரையான் in Tamil, travel from the soil through cracks as thin as a hair to reach door frames, cupboards and stored paper. The barrier only works if it is unbroken under and around the whole building.

Next question: At which stages is it applied? More

Types of termite protection

Termite protection methods and the standards behind them
MethodWhenReference
Pre-construction chemical soil treatmentDuring construction, in stagesIS 6313 (Part 2)
Post-construction drill-and-inject treatmentExisting buildingsIS 6313 (Part 3)
Treated or naturally resistant timberDoors, frames, joineryTimber treatment by the joinery supplier
Keeping wood debris out of fillsDuring constructionGood site practice

Next question: Pre- or post-construction for my house? More

Pre-construction or later?

Treating soil before the floor is laid reaches every square metre under the building. Drilling and injecting later can only reach what the drill holes reach, and it means breaking tiles and skirting.

The extra cost of doing each stage properly is small next to replacing termite-damaged frames and cupboards.

On a new house, pay for the full staged pre-construction treatment with a written warranty. Keep post-construction drilling for buildings that already exist.

Next question: What are the stages exactly? More

The treatment stages, in order

IS 6313 (Part 2) and the product label set the concentration and the litres per square metre for each stage. Ask for them in writing.

  1. Foundation trenches: bottom and sides, after excavation and before the PCC bed.
  2. Backfill against the foundation: treated layer by layer as it is placed.
  3. Plinth fill: the top of the compacted fill under the ground floor, just before the floor PCC.
  4. Wall-floor junction: a channel along the inside of the walls, before the floor is laid.
  5. External perimeter: soil along the outside of the plinth, after construction and before aprons or paving.
  6. Pipes and conduits entering the building: the soil around them.

Next question: How do I make sure each stage was done? More

What to check with the applicator

  1. Ask for the operator's pest control licence and the chemical's registration number from the Central Insecticides Board and Registration Committee on the label.
  2. Get the chemical, dilution and litres per m² for each stage in writing.
  3. Have someone from your side present at every stage; the treatment is invisible afterwards.
  4. Make sure treated soil is not dug up again; if it is, have it re-treated.
  5. Collect a stage-wise record and the warranty letter.

Next question: Any precautions on site? More

Site precautions

  • Chemicals stay with the applicator; do not keep leftovers on site.
  • Keep the treatment away from open wells and the sump excavation.
  • Avoid treating just before heavy rain; reschedule the stage if a downpour is forecast.
  • Workers handling treated soil should wear gloves and wash before eating.

Next question: What goes into the trench after treatment? More

Mistakes that leave gaps in the barrier

  • Treating only the trench bottom and calling the job done.
  • Leaving the treated plinth fill for weeks while workers dig and dump on it before the floor PCC.
  • Skipping the external perimeter once paving goes in.
  • Leaving formwork offcuts, wooden pegs and paper bags in the plinth fill; they feed termites.
  • Paying a lump sum without a written stage plan.

Next question: Which wood resists termites for door frames? More

Questions buyers ask

Anti-Termite Treatment: questions buyers ask

When to apply anti-termite treatment?

In stages during construction: trench bottom and sides before the PCC bed, backfill as it is placed, the plinth fill just before the ground-floor PCC, the wall-floor junction, and the outside perimeter at the end. One visit at the start is not a complete treatment.

What is the recommended ratio of anti-termite chemical to water for pre-construction treatment?

It depends on the chemical. IS 6313 (Part 2) and the product label give the concentration and the litres per square metre for each stage. Ask the applicator to write the chemical, dilution and dose in the quote, and never let labourers mix it by eye.

What is the best anti-termite liquid for construction?

We do not name products. Use a termiticide registered for soil treatment with the Central Insecticides Board and Registration Committee, applied by a licensed operator at the dose IS 6313 (Part 2) and the label set. Registration and correct application matter more than the brand.

Which is the best anti-termite treatment?

For a new building, full pre-construction soil treatment at every stage, because it builds an unbroken barrier under the whole structure. Post-construction drill-and-inject treatment is meant for existing buildings and is harder to make continuous.

Should anti-termite treatment come with a warranty?

Ask for one in writing, listing the stages, chemical and doses. Read what it requires from you, such as not disturbing treated soil or informing the operator before later excavation.

Need Anti-Termite Treatment with your order?

Call, WhatsApp or send the quote form with it filled in: a partner supplier quotes, supplies and bills it, and we time it with your loads.

WhatsApp